BJP vows Bengal highway bonanza. Past record is filled with red flags, hope is double engine

On August 5 this year, Nitin Gadkari told Parliament that 21 national highway projects in Bengal, covering 193 km and involving investments of Rs 6,690.87 crore, were running behind schedule

Kolkata, November 27, 2026, dmanewsdesk: Bengal is being promised a highway bonanza even as several critical road projects across the state remain in limbo, held up by land acquisition hurdles, prolonged construction and mounting costs.

On Thursday, Union road transport and highways minister Nitin Gadkari put road projects worth Rs 1 lakh crore on the table, including Rs 14,000 crore earmarked for the Kolkata ring road and Rs 25,000 crore for national highways, over and above Rs 35,000-crore worth of ongoing works.

Bengal chief minister Suvendu Adhikari welcomed the package and pledged land and faster clearances to facilitate the projects.

“I am not among those who make announcements and leave. Whatever I promise, I will deliver,” Gadkari said, invoking the Centre’s “double-engine” pitch.

Assuring Adhikari that funding would not be a constraint, he added: “Do not worry about money. You will get tired of asking for projects but I will not get tired of providing funds.”

But can the sums and the double-engine promise translate into completed roads?

The record of existing national highway projects in Bengal suggests there is reason for caution. Several projects remain unfinished years after their original deadlines, with prolonged construction and rising costs.

On August 5 this year, Gadkari told Parliament that 21 national highway projects in Bengal, covering a combined length of 193 km and involving a total investment of Rs 6,690.87 crore, were running behind schedule.

Gadkari said this in a written response to Trinamool Congress MP Menaka Guruswamy, who had sought details of delayed highway projects in the state.

On the same day, another Trinamool MP, Derek O’Brien, sought details of the projects running behind schedule, the reasons for the delays and the additional expenditure arising from them.

The Telegraph Online’s analysis of the ministry’s replies found that the NH-32 Purulia-Chandil road rehabilitation project recorded the highest cost escalation among the 21 delayed projects, at Rs 51 crore.

It was followed by the NH-12 Farakka Ganga bridge project, which saw an increase of Rs 24 crore.

The 13 km NH-81 missing link between Harishchandrapur and Kalindri Bridge in Malda in north Bengal was originally scheduled for completion on November 2, 2018. Its revised deadline is October 31, 2026, a delay of nearly eight years.

The NH-12 Ganga bridge project near Farakka was initially scheduled for completion on December 20, 2021. It has been delayed by nearly five years.

All three projects were scheduled for completion between September and October this year, but there has been no confirmation that they have been completed.

The ministry’s replies point to a familiar set of obstacles behind the delays: land acquisition, railway clearances, removal of encroachments, forest clearances, disruption to construction during the pandemic, contractor-related problems and delays in the supply of materials.

Take the construction of a six-lane elevated corridor over the existing Kona Expressway (NH 117) to ease traffic congestion near Santragachi station and bus terminus, Shibpur and Canal Side Road.

The corridor was originally scheduled to be ready by December 2026. Yet, by July this year, barely 40 per cent of the work had been completed.

The deadline has since been pushed back by another year, to December 2027.

Source: The Telegraph online